Grupa Azoty Puławy has decided to issue and deliver a debit note to the Contractor of the 100 MWe coal-fired power unit project (the Polimex Mostostal S.A. consortium) for over PLN 239 million as a contractual penalty for the termination of the contract due to reasons attributable to the Contractor.